24 August 2021 : Morning Shift |
Question. 15.
Download Our AppThe vertices of a Δ ABC lie on a circle with centre O. AO is produced to meet the circle at the point P. D is a point on BC such that AD ⊥ BC. If ∠B = 68° and ∠C = 52°, then the measure of ∠DAP is:
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
AD ⊥ BC
∠B = 68°
∠C = 52°
Calculation:
Join O to B where point O is the circum centre of the triangle.
⇒ ∠BOA = 2∠BCA
⇒ 2 × 52°
⇒ 104°
In ΔBOA
⇒ OB = OA [radius of the circle]
⇒ ∠OBA = ∠OAB
⇒ ∠AOB + ∠OAB + ∠OBA = 180°
⇒ 2∠OAB = (180° – 104°)
⇒ 2∠OAB = 76°
⇒ ∠OAB = (76/2)
⇒ ∠OAB = 38°
In ΔABD
⇒ ∠ABD + ∠BDA + ∠DAB = 180°
⇒ ∠DAB = (180° – 90° – 68°)
⇒ ∠DAB = 22°
Now,
∠DAP = ∠BAO – ∠BAD
⇒ ∠DAP = (38° – 22°)
⇒ ∠DAP = 16°
So, the required value is 16°
Question. 16.
Download Our AppA can complete a work in 11(1)/(2) days. B is 25% more efficient than A and C is 50% efficient than B.Working together A. B and C will complete the same work.
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
Time taken to complete a work by A = days = 23/2 days
B is 25% more efficient than A = (25/100) = 1/4
Efficiency of A = 4 days
Efficiency of B = (4 + 1) = 5 days
C is 50% efficient than B = (50/100) = 1/2
Efficiency of C = (5/2) = 2.5 days
Formula used:
Work = Efficiency × Time
Calculation:
Total work = (23/2 × 4) = 46 days
Total time taken by A, B and C together = [46/(4 + 5 + 2.5)] days
⇒ (46/11.5) days
⇒ 4 days
∴ The required time is 4 days
Shortcut Trick:-
Efficiency of them
So, total work = 8 × 23/2 = 92 units
Total time taken by A, B and C together = [92/(8 + 10 + 5)] = 4 days
Question. 17.
Download Our AppThe average of 23 numbers is 51.The average of first 12 numbers is 49 and the average of last 12 numbers is 54.If the twelfth number is removed then the average of the remaining numbers (correct to two decimal places) is:
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
The average of 23 numbers = 51
The average of first 12 numbers = 49
The average of last 12 numbers = 54
Formula used:
Average = sum of observations/Number of observations
Calculation:
The sum of 23 numbers = (23 × 51) = 1173
The sum of first 12 numbers = (12 × 49) = 588
The sum of last 12 numbers = (12 × 54) = 648
Now,
The twelfth number = [(588 + 648) – 1173]
⇒ (1236 – 1173)
⇒ 63
The 12th number = 63
Now, If the twelfth number is removed,
The sum of remaining numbers = (1173 – 63) = 1110
The average of remaining number = (1110/22)
⇒ 50.45
∴ The required average number is 50.45
Question. 18.
Download Our AppThe total mumber of students in a school is 1400 out of which 35% of the students are girls and the rest are boys.If 50% of the boys and 90% of the girls passed in an ammal examination then the percentage of the students who failed is:
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
The total number of students in a school = 1400
Number of girls = 35%
Number of boys who passed an annual examination = 80%
Number of girls who passed an annual examination = 90%
Calculation:
The total number of students in a school = 1400
Number of girls = (1400 × 35/100)
⇒ 490
Number of boys = (1400 – 490) = 910
Number of boys who passed an annual examination = (80% of 910)
⇒ (80/100 × 910)
⇒ 728
Number of boys who failed the annual examination = (910 – 728) = 182
Number of girls who passed an annual examination = (90% of 490)
⇒ (90/100 × 490)
⇒ 441
Number of girls who failed the annual examination = (490 – 441) = 49
Now,
Total number of failed students = (182 + 49) = 231
Required percentage of failed students = (231/1400 × 100)
⇒ (231/14)
⇒ 16.5%
∴ The required percentage of failed students is 16.5
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
x + 1/x = 7
Formula used:
x + 1/x = k
⇒ x2 + 1/x2 = (k)2 – 2
Calculation:
x + 1/x = 7
⇒ x2 + 1/x2 = (7)2 – 2
= 49 – 2 = 47
Question. 20.
Download Our AppIn a triangle ABC, length of the side AC is 4 cm more than 2 times the length of the side AB. Length of the side BC is 4 cm less than the three times the length of the side AB. If the perimeter of ΔABC is 60 cm, then its area (in cm2) is:
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
Length of the side AC is 4 cm more than 2 times the length of the side AB
Length of the side BC is 4 cm less than the three times the length of the side AB.
The perimeter of ΔABC = 60 cm
Formula used:
Area of triangle = 1/2 × base × height
Calculation:
Let the side of AB be x cm
Then,
Length of the side AC is 4 cm more than 2 times the length of the side AB = (2x + 4) cm
Length of the side BC is 4 cm less than the three times the length of the side AB. = (3x – 4) cm
Perimeter of ΔABC = 60 cm
⇒ (x + 2x + 4 + 3x – 4) = 60
⇒ 6x = 60
⇒ x = 10 cm
Now,
Side of AB = x = 10 cm
Side of AC = (2x + 4) = (2 × 10 + 4) = 24 cm
Side of BC = (3x – 4) = (3 × 10 – 4) = 26 cm
We know that 10, 24, and 26 is a triplet,
⇒ We can say that the given triangle is a Right angle triangle.
Now,
⇒ Area of triangle = 1/2 × base × height
Area of triangle = (1/2 × 10 × 24)
⇒ (5 × 24)
⇒ 120 cm2
∴ The required area is 120 cm2
Question. 21.
Download Our AppIf 2x + 3y + 1 = 0, then what is the value of (8x3 + 8 + 27y3 - 18xy)?
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
2x + 3y = 1
Formula used:
(a + b)3 = a3 + b3 + 3ab(a + b)
Calculation:
According to the question
2x + 3y + 1 = 0
⇒ 2x + 3y = -1
Now,
(2x + 3y)3 = (2x)3 + (3y)3 + 3 × 2x × 3y (-1) = -1
⇒ 8x3 + 27y3 – 18xy = -1
Now,
The value of (8x3 + 8 + 27y3 – 18xy) = (8 – 1)
⇒ 7
∴ The required value is 7
Question. 22.
Download Our AppA sum of Rs. 9500 amounts to Rs. 11495 in 2 years at a certain rate percent per annum, interest compounded yearly. What is the simple interest (in Rs. ) on the same sum for the same time and double the rate?
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
Amount = Rs. 11495
Principal = Rs. 9500
Time = 2 years
Formula used:
A = P(1 + r/100)t
SI = (P × R × T)/100
Calculation:
A = P(1 + r/100)t
⇒ 11495 = 9500(1 + r/100)2
⇒ (1 + r/100)2 = (11495/9500)
⇒ (1 + r/100)2 = (121/100)
⇒ (1 + r/100)2 = (11/10)2
⇒ r = 10%
Now,
According to the question
Principal = Rs. 9500
Rate = double the rate = (2 × 10) = 20%
Time = 2 years
SI = (P × R × T)/100
⇒ Rs. (9500 × 20 × 2)/100
⇒ Rs. (95 × 20 × 2)
⇒ Rs. 3800
∴ The required SI is Rs. 3800
Question. 23.
Download Our AppTable shows income (in Rs.) recieved by 4 employee of a company during the month of December 2020 and all their income sources.
Source | Amit | Suresh | Nitin | Varun |
Salary | 35000 | 38500 | 29000 | 42000 |
Arrears | 6000 | 6300 | 5000 | 7500 |
Bonus | 1000 | 1100 | 1000 | 1240 |
Overtime | 1800 | 1950 | 1400 | 1500 |
By what percent is the bonus of Varun less than the bonus of Amit and Nitin taken together?
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelCalculation:
Bonus amount for Varun = Rs.1240
Bouns amount for Amit and Nitin = 1000 + 1000 = Rs.2000
Required % = (2000 - 1240)/2000 × 100 = 38%
∴ Bonus of Varun is 38% less than the bonus of Amit and Nitin taken together.
Answer (Detailed Solution & Explanation Below)
Solution & Explanation
Subscribe Our You Tube ChannelGiven:
Formula used:
(a2 – b2) = (a + b)(a – b)
sec2α = 1/cos2α
1/cosecα = sinα
1 – sin2α = cos2α
Calculation:
⇒ 1/cos2α (1 + sinα)(1 – sinα)
⇒ 1/cos2α (12 – sin2α)
⇒ 1/cos2α (1 – sin2α)
⇒ 1/cos2α × (cos2α)
⇒ 1
∴ The required value is 1
Question. 25.
Download Our AppThe value of 3(1)/(5)-:4(1)/(2) of 5(1)/(3)-(1)/(8)-:(1)/(2) of (1)/(4)+(1)/(4)((1)/(2)-:(1)/(8)times(1)/(4)) is :
Answer (Detailed Solution & Explanation Below)
BODMAS का उपयोग करके सरलीकृत कीजिए: कोष्ठक - का (of) - भाग - गुणा - जोड़ - घटाना